Open the Irish energy regulator's Regulatory Framework Paper at PDF page 190. A table of 29 priority grid projects begins there. Row one is the North South 400 kilovolt (kV) interconnector, 101 km of new overhead line. In the column for construction start, its cell reads 1 June 2026.
Now turn to EirGrid, the grid operator. EirGrid's project page, read on 16 November 2026, says "We are now at Step 6", the stage it labels construction. Its latest update, from March 2026, records no start of works. The Irish Times reported the Minister for Energy on 14 October saying work should begin next year. It reported a Minister of State on 5 November telling the Dáil that "construction is commencing". Those two reports, three weeks apart, do not sit easily together.
In our view Ireland has approved the money and printed the dates, and the regulator's own tables show the dates are the weaker half. A printed date is a plan. If you build substations or lay cable, the tables below are your market.
The number: €13.8 billion. That is what the regulator, the Commission for Regulation of Utilities (CRU), has allowed for electricity networks in 2026 to 2030, which it calls "an 80% increase" on the €7.64 billion spent in the previous five years. Our sum: 13.78 divided by 7.64 is 1.8.
The money is a starting allowance that can rise, and on our sum ESB Networks holds about 82% of it. Seven of the 29 priority projects had a listed construction start on or before 16 November 2026, on the regulator's own table. We could not confirm from public records that any of the seven has started. We asked ESB Networks and EirGrid on 16 November. Neither had replied by our deadline of 5pm on 20 November.

Seven of the 22 dated starts have passed
The table on pages 190 and 191 of the Regulatory Framework Paper covers 29 projects, all on the high-voltage grid (110 kV to 400 kV). In the construction-start column, seven rows say "Completed", which the paper does not explain, and 22 carry a date. Seven of those 22 dates fell on or before 16 November 2026.
They are Belcamp's 220 kV busbar extension, listed for 11 March 2026, then four listed for 1 June 2026 and two cables listed for 1 September 2026.
Nowhere does the table define a start, so it may mean early site works. Two award notices in the EU's tenders journal add dates. A building and civil works contract at Belcamp 220 kV substation was concluded on 26 June 2026. That is more than three months after the listed start for the Belcamp busbar extension. The notice values it at €11.2 million, names Elliott Building and Civil Engineering Limited and records six tenders. It does not say whether this is the busbar extension itself. A design and build contract for a Finglas to North Wall 220 kV cable replacement was concluded with GMC Utilities Group Limited on 29 September 2026. That is four weeks after the listed start for the cable of the same name. A contract date does not tell us when works began.
Fifteen of the 29 have a final date for being energised, meaning switched on, in 2031 or later, after the five years the money covers. Where the table prints lengths, they come to 179 km of new overhead line, 277 km of line upgrades and 199 km of new underground cable, on our sum.
The 27 substations have prices and no dates
A second table, on pages 181 and 182 of the same paper, lists 27 new 110 kV substations on the local network, each with a cost. They are separate from the 29 projects. The cheapest is Bracklone at €10.9 million and the dearest North City Junction at €44.7 million, and the 27 come to €679.6 million on our sum. The table prints no county and no date, though on our reading the names point to a county for 13.

The €18.9 billion headline is the high case
The headline figure comes from the regulator's own press notice, headed "CRU Approves Record Investment in Ireland's Electricity Grid and Network". It leads with investment of "up to €18.9bn", a high estimate that its summary paper says "should not be viewed as a cap".
Measure it against Table 1 on page 9 of that summary paper. The starting allowance, or baseline, is €13.8 billion, and €3.75 billion of that is running costs. That leaves €10.0 billion of capital, of which the 29 projects take €2.0 billion.
Tender lists are open, and award notices name eight firms
ESB buys through qualification systems, standing lists of approved firms from which it later calls tenders. We found 13 of them listed for network work on eTenders, the Government tendering site, on 16 November 2026, and read each one.
CON1140 covers large substations at 110 kV, 220 kV and 400 kV. Its notice expects many to be built from 2026 to 2035, and the first framework under it closed to applicants on 27 June 2025. CON1199 covers substation works on the local network, with a first closing date of 17 July 2026. Both notices say applications "may be made" to join "at any time". Five of the 13 say so, and the table below gives every reference.
None of the notices we read shows a value, names an appointed contractor or gives a date for the next call. A list is an invitation to wait, though it is the queue that leads to the work.

Award notices name the firms that won. ESB's overhead lines framework, concluded in February 2024, names eight firms: Circet Networks Ireland, Gaeltec Utilities, Energoinvest Reach Active, Grid Team Services, TLI Group, Murphy International, KTL and Actavo (Ireland). Its notice carries a total value of €1.2 billion, a figure for the whole framework and not for any one firm. Grid Team Services has no connection with GridteamAI or this publication.
A framework for building the North South interconnector's overhead line was concluded with four contractors on 7 June 2024, at a total value of €384 million in its notice. ESB's poling framework, concluded in July 2025, took 24 firms from 25 tenders, with a maximum value of €247 million across all of them.

The case against
The objection to our caution runs like this. The regulator has approved the money and printed dates for each of the 29 priority projects. It has also ring-fenced the critical work and set 26 incentives, with penalties attached for falling short.
Our answer is in the sizes. ESB Networks' two penalty limits together come to about €80 million a year. Its baseline spending is roughly €2.3 billion a year, so on our sum the penalty is 3.5%. The regulator's transmission paper says underspending on the grid in the previous five years "was driven in-part by an under-delivery of overhead lines". It also records that final dates for the 29 moved between two versions of the plan, from 12 months earlier to 34 months later. The average was three months later. The last plan under-delivered on overhead lines.
What it means for you
Your order book. On Monday, find your trade's reference in the eTenders table above and apply to join it. Then ask ESB when the next call under it comes. In our view a smaller firm's quicker way in may be through the framework holders named above.
Your programme. Treat every listed date as the earliest possible. Seven have passed without a start we could confirm.
Who pays, who gains. Electricity customers pay. The regulator expects a typical household's network charge to rise by about €12 a year on the baseline and up to €21 in the high case. In our view the gainers are contractors already on ESB's lists.
How we could be wrong
The seven. If ESB Networks or EirGrid confirms by 31 January 2027 that most are under construction, the timetable is holding.
Kildare Meath. Its 51 km of underground cable is listed to start on 15 February 2027. If it starts on time, score one against us.
We do not know two things. Who holds the substation frameworks, since we found no award notice under CON1140 or CON1199. Where the other 14 substations are, and when any of the 27 starts.
The short version
The regulator's baseline for networks to 2030 is €13.8 billion, 80% up, and one buyer, ESB Networks, holds about 82% of it.
Seven of the 22 dated priority projects had a listed start that has passed. Award notices show two contracts, at Belcamp and for Finglas to North Wall, concluded after those dates.
A printed date is a plan.
We'll keep score.
If you are on one of the seven, tell us whether it has started. Hit reply.
If a colleague bids for Irish grid work, forward this.
The Wire covers UK and Irish infrastructure news every weekday morning, and it's free. Our Ireland page follows the build, and the live map tracks more than 1,000 projects.
Next week: how the regulator counts a power line as on time.
See you next week.
Anthony
Update, 23 November 2026: EirGrid has replied to our question, and its reply answers a different one. We had asked whether construction has started on seven priority grid projects whose listed start dates have passed. About two hours after our piece on Ireland’s grid went out that morning, EirGrid’s press office wrote that “EirGrid publishes regular updates on the status of transmission infrastructure projects” and sent us to its quarterly reports.
Anyone told that status updates are published would expect them to say whether work has begun, and these do not. The latest report shows dates as of 30 September 2026 and follows more than 400 projects through four milestones, none of which is a construction start. What it records instead is approvals and switch-on dates, such as the signing of the project agreement between EirGrid and ESB Networks.
Two of the seven show how far such dates can move. For the signing of the North South interconnector’s agreement the report gives a baseline of 3 February 2026, set by the regulator, the Commission for Regulation of Utilities, and a forecast of 31 March 2027. That baseline has already passed, and by our sum the forecast sits 421 days beyond it, or about fourteen months.
For the Dunstown series capacitor the final switch-on moved from 31 December 2027 in the regulator’s baseline to 3 September 2029 in the report’s forecast. That is about twenty months later, on a date that is still nearly three years away.
An agreement and a switch-on are different measures from a start on site, so work may have begun on either project and the question stands. In our view a business with crews or a tender tied to either project should plan to the report’s forecasts and not to the listed starts. ESB Networks had not replied by midday on 23 November.
A printed date is still a plan, even with a newer one printed beside it.
Sources
Commission for Regulation of Utilities, Price Review Six, Summary Paper, CRU2025193, 16 December 2025 (baseline of €13,779.6 million and high case of €18,875.8 million for 2026 to 2030, in 2024 prices; baseline capital €10,029.3 million and running costs €3,750.3 million; capital by body: ESB Networks' local network €5,864.7 million and grid building €3,016.0 million, EirGrid €716.9 million onshore and €431.7 million offshore; the high case "should not be viewed as a cap"; "an 80% increase on current outturn expenditure" in 2021 to 2025, when €7,641.3 million was spent; €2,012.0 million ring-fenced for the 29 priority projects and €1,080.7 million for high-voltage reinforcement; 27 new 110 kV substations; 26 incentives; yearly penalty limits of €64.36 million and €15.54 million, both ESB Networks'; household network charge up about €12 a year, or as much as €21 in the high case): https://cruie-live-96ca64acab2247eca8a850a7e54b-5b34f62.divio-media.com/documents/CRU2025193_-_Price_Review_Six_-_Final_Determination_-_Summary_Paper.pdf
Commission for Regulation of Utilities, Price Review Six, Regulatory Framework Paper, CRU2025197, 16 December 2025 (table of 29 priority projects, pages 190 and 191, with construction start, first and final switch-on dates, kilometres and voltages as printed in project names; table of 27 new 110 kV stations with costs from €10.9 million to €44.7 million, pages 181 and 182, with no county and no date): https://cruie-live-96ca64acab2247eca8a850a7e54b-5b34f62.divio-media.com/documents/CRU2025197_-_Price_Review_Six_-_Final_Determination_-_Regulatory_Framework_Paper.pdf
Commission for Regulation of Utilities, Price Review Six, Transmission Paper, CRU2025195, 16 December 2025 (underspend "driven in-part by an under-delivery of overhead lines"; final switch-on dates for the 29 projects "ranging from being brought forward 12 months to delayed by 34 months (average delay of 3 months)"): https://cruie-live-96ca64acab2247eca8a850a7e54b-5b34f62.divio-media.com/documents/CRU2025195_-_Price_Review_Six_-_Final_Determination_-_Transmission_Paper.pdf
Commission for Regulation of Utilities, "CRU Approves Record Investment in Ireland's Electricity Grid and Network", 16 December 2025, a press notice and not the determination ("up to €18.9bn"; "69 new or updated substations"): https://www.cru.ie/about-us/news/cru-approves-record-investment-in-irelands-electricity-grid-and-network/
ESB notices on eTenders, the Government tendering site, read on screen on 16 November 2026: 13 qualification systems for network work listed. Quoted here: CON1140, at-scale substations at 110 kV, 220 kV and 400 kV, published 24 April 2025 ("during the period 2026 - 2035"; "Framework for PR6 Capacity"; first closing date 27 June 2025; "applications may be made to join the Qualification System at any time"; estimated value blank): https://www.etenders.gov.ie/epps/cft/prepareViewCfTWS.do?resourceId=5529950 ; CON1199, distribution substation works up to 110 kV, published 8 June 2026 (first closing date 17 July 2026; applications "at any time"): https://www.etenders.gov.ie/epps/cft/prepareViewCfTWS.do?resourceId=8285687 ; D20/CON/006, overhead lines "at all voltages": https://www.etenders.gov.ie/epps/cft/prepareViewCfTWS.do?resourceId=3324082 ; D20/CON/911, major cable projects in two categories: https://www.etenders.gov.ie/epps/cft/prepareViewCfTWS.do?resourceId=3509897 ; D20/CON/882, substation design and build: https://www.etenders.gov.ie/epps/cft/prepareViewCfTWS.do?resourceId=3461954 ; D20/CON/500, poling: https://www.etenders.gov.ie/epps/cft/prepareViewCfTWS.do?resourceId=3389197 . All 13 pages were opened and read on 16 November 2026. Also D20/CON/1060, Belcamp Substation Building and Civil Works, published 14 November 2024, deadline 16 December 2024: https://www.etenders.gov.ie/epps/cft/prepareViewCfTWS.do?resourceId=4670380
EirGrid, North South Interconnector project page, read 16 November 2026 ("We are now at Step 6", labelled construction, energisation and benefit sharing; latest update dated March 2026; no start of works recorded): https://www.eirgrid.ie/community/projects-your-area/north-south-interconnector
The Irish Times, 14 October 2026, a press report (the Minister for Energy saying work should begin on the project next year): https://www.irishtimes.com/business/2026/10/14/work-on-north-south-power-line-to-start-next-year-minister/
The Irish Times, 5 November 2026, a press report of Dáil questions (a Minister of State: "The planning conditions are commencing and construction is commencing"): https://www.irishtimes.com/politics/2026/11/05/contentious-north-south-electricity-interconnector-to-run-overground-despite-opposition/
Contract award notices in the EU's tenders journal, TED, read on 16 November 2026 through its public search service (buyer Electricity Supply Board), with the Belcamp and Finglas notice pages also opened and read on screen that day: D20/CON/1060, Belcamp 220 kV substation building and civil works, Elliott Building and Civil Engineering Limited, €11,175,000, six tenders, concluded 26 June 2026: https://ted.europa.eu/en/notice/-/detail/592371-2026 ; D20/CON/911_T02, Finglas Northwall 220 kV cable replacement, design and build, GMC Utilities Group Limited, value printed as 0, three tenders, concluded 29 September 2026: https://ted.europa.eu/en/notice/-/detail/767868-2026 ; D20/CON/507, overhead lines framework, eight firms, total value €1,200,000,000, concluded 14 February 2024: https://ted.europa.eu/en/notice/-/detail/192257-2024 ; D20/CON/864, North South 400 kV interconnector overhead line construction framework, four contractors, total value €384,169,012, five tenders, concluded 7 June 2024: https://ted.europa.eu/en/notice/-/detail/399775-2024 ; D20/CON/1057, poling framework, 24 firms from 25 tenders, maximum value €247,000,000, concluded 16 July 2025: https://ted.europa.eu/en/notice/-/detail/571446-2025
Our own enquiry: on 16 November 2026 we asked ESB Networks and EirGrid whether any of the seven projects with a listed construction start on or before that date has started, with a deadline of 5pm on 20 November 2026 for a reply. Neither had replied by then. The table the question refers to: https://cruie-live-96ca64acab2247eca8a850a7e54b-5b34f62.divio-media.com/documents/CRU2025197_-_Price_Review_Six_-_Final_Determination_-_Regulatory_Framework_Paper.pdf
Our sums and counts, from items 1 and 2, with dates from the award notices: 11 March to 26 June 2026 is 107 days, and 1 to 29 September 2026 is 28 days. ESB Networks' share: its baseline is 3,220.5 plus 8,141.4, which is 11,361.9, and divided by 13,779.6 is 82%. The increase: 13,779.6 divided by 7,641.3 is 1.80. Capital: 5,864.7 plus 3,016.0 plus 716.9 plus 431.7 is 10,029.3, and EirGrid's two figures make 1,148.6, about €1.1 billion. A fifth: 2,012.0 divided by 10,029.3 is 20%. Substations: the 27 printed costs add to €679.6 million. Penalties: 64.36 plus 15.54 is 79.9, about €80 million a year, while 11,361.9 divided by 5 years is 2,272, about €2.3 billion a year, and 79.9 divided by 2,272 is 3.5%. Project table: 29 rows, of which 7 show "Completed" and 22 a date in the construction start column; 7 of the 22 dates are on or before 16 November 2026 (one on 11 March, four on 1 June and two on 1 September 2026); 15 rows show a final switch-on dated 2031 or later. Reports: 14 October to 5 November 2026 is 22 days, about three weeks. Substation names: a county can be read from 13 of the 27, leaving 14. Lengths, from the 29-project table where it prints them: new overhead line 101.0 plus 2.7 plus 75.0 is 178.7 km, line upgrades come to 277.4 km and new underground cable to 199.3 km. Tender lists saying applications may be made at any time: CON1140, CON1199, D20/CON/882, CON 1077 and Con 897, which is five of the 13: https://cruie-live-96ca64acab2247eca8a850a7e54b-5b34f62.divio-media.com/documents/CRU2025197_-_Price_Review_Six_-_Final_Determination_-_Regulatory_Framework_Paper.pdf